Installation
Installation Guide



Installation 1

 

Installation Basics
  • The polymer concrete must always be installed on a concrete layer (stabilizator)

  • The quality and dimensions of the concrete envelope will depend on the load class according
    to the official norms. The absolute minimum thickness is 10cm.

  • The superior edges of the channels must be installed 3mm below the surface.

  • The polymer concrete channels fulfill the requirements of the indicated class after the envelope is hardened. Before this, heavy loads are strictly to be avoided.

step1 step2 step3
Step 1: Start Step 2: Installation of a layer of
concrete or stabilizator
Step 3: Installation of the first channel
step4 step5 step6
Step 4: Next channel Step 5: Installation of the gratings
or temporary covers
Step 6: Install concrete envelope
step7 step8 step9
Step 7: Seal channel joints Step 8: Install gratings Step 9: Installation finished
 
Specific installation guide per product family
PDF Self PDF Selfplast PDF Proself
PDF Plus 100 PDF Plus 150/200/300 PDF Max 100
PDF Max 150/200/300 PDF Flush 100/200  
 
 
  disclaimer welle disclaimer welle polyalfa